Phase 1 — Graph-Primary Core and the Deployment Plane (Status)

Unit type: Phase Unit ID: phase-1 Status: ⏳ Not started — blocked on Phase 0 exit gate Last updated: 2026-09-22 Plan: phase-1-plan.md Sketch: phase-1-sketch.md


Current state

Decomposed from the epic on 2026-09-22. No slice has started. Cannot start until phase-0-status.md records its exit gate as passed.

Blockers

Blocker Detail
Phase 0 exit gate Hard dependency, per the epic
SPI inventory doc placement See phase-1-plan.md §2 — confirm docs/architecture/spi-inventory.md before P1.11.2
apps/* naming Carried from Phase 0’s decomposition findings — first actually touched by P1.10

Milestone tracker

Milestone Demonstrable outcome Status
M2 Graph-primary lifecycle (Surface revision authored/reviewed/approved entirely in the graph, no relational ledger) Not demonstrated
M3 Pack + activation (signed pack, activated with diff/SHADOW/promote/rollback, Activation Console) Not demonstrated

Next steps

  1. Wait for Phase 0 exit gate.
  2. Confirm SPI inventory doc placement and apps/* naming (low urgency, cheap to resolve now).
  3. Begin P1.1 (Surface lifecycle → graph).