Unit type: Phase
Unit ID: phase-1
Status: ⏳ Not started — blocked on Phase 0 exit gate
Last updated: 2026-09-22
Plan: phase-1-plan.md
Sketch: phase-1-sketch.md
Decomposed from the epic on 2026-09-22. No slice has started. Cannot start until phase-0-status.md records its exit gate as passed.
| Blocker | Detail |
|---|---|
| Phase 0 exit gate | Hard dependency, per the epic |
| SPI inventory doc placement | See phase-1-plan.md §2 — confirm docs/architecture/spi-inventory.md before P1.11.2 |
apps/* naming |
Carried from Phase 0’s decomposition findings — first actually touched by P1.10 |
| Milestone | Demonstrable outcome | Status |
|---|---|---|
| M2 | Graph-primary lifecycle (Surface revision authored/reviewed/approved entirely in the graph, no relational ledger) | Not demonstrated |
| M3 | Pack + activation (signed pack, activated with diff/SHADOW/promote/rollback, Activation Console) | Not demonstrated |
apps/* naming (low urgency, cheap to resolve now).