Phase 3 — Operation Plane (Status)

Unit type: Phase Unit ID: phase-3 Status: ⏳ Rolling-wave placeholder — not started, full expansion awaits P2.11.4 Last updated: 2026-09-22 Plan: phase-3-plan.md Sketch: phase-3-sketch.md


Current state

Decomposed from the epic on 2026-09-22 as a rolling-wave placeholder.

Blockers

Blocker Detail
Phase 2 exit gate Hard dependency
C-07 reconciliation green for one week Hard internal gate before any C-09 slice, restated in phase-3-plan.md
Full VP-level slice expansion Scheduled at P2.11.4

Milestone tracker

Milestone Demonstrable outcome Status
M7 Projections live Not demonstrated
M8 Tanks respond Not demonstrated
M9 Write-back Not demonstrated

Next steps

  1. Wait for Phase 2 exit gate.
  2. At P2.11.4, expand this phase to full VP-level detail.